Condition Assessment Audit of Steam Plants
A 3 to 4 day plant audit to evaluate the state of the main cycle components and piping, assess remaining life and fitness for service, and recommend inspection and life extension activities.  This audit is typically the first step of plant-wide condition assessment and component life evaluation for the non-electrical systems.  Utility and industrial steam plants and related equipment.  
Note:  The Water Chemistry and Corrosion Control Plant Audit can be performed during the same plant visit.  
Objectives
The objectives of the audit are:
Safety assurance of the mechanical equipment - main cycle components
Minimizing forced outages and maintenance costs
Operation at best achievable efficiency (heat rate)
Background
Increasing equipment life leads to more frequent forced outages, higher maintenance costs, and safety problems.  The cost of these problems can be up to $10,000 of lost electric production and $1 million a day of lost industrial production.
The main cycle components, condition of which deteriorates with time, include:
Boilers (waterwall tubes, superheater, reheater, headers)
High temperature piping
Feedwater piping
Turbines
Deaerators
Heaters and other auxiliary equipment
Condensers
Valves
Steam Traps

The safety related damage mechanisms are:  
Creep
Low Cycle Corrosion Fatigue (LCCF)
Thermal (low cycle) Fatigue
High Cycle Corrosion Fatigue (HCCF)
Stress Corrosion Cracking
Flow-Accelerated Corrosion
Cavitation
Water Hammer

Technology exists to properly inspect equipment, determine the damage mechanisms and root cause, and repair or replace the damaged components.  
The safety issues experienced in steam systems are shown in the table below:

Component
Damage Mechanism [1]
Major Influences [2]
Destructive Failures [3]
$ Impact [4]
Steam Piping
Creep
Welds, temperature, time
Y
10^7
LCF, LCCF
Temperature changes
Carbon steel graphitization
Temperature and time
Drums and Headers
LCF, LCCF, SCC
Temperature cycling, design, water chemistry
N
10^7
Boiler Tubes
LCCF (20 others)
Water chemistry, cycling, heat flux, etc.
N
10^5
Feedwater and
Wet Steam Piping
FAC
Design, water chemistry
Y
10^7
Cavitation
Design, operation
Y
SCC
Residual stress, chemistry
N
CF, LCCF
Weld quality, water chemistry, temperature changes
N
Deaerator, Flash Tank, Hot Water and Steam Vessels - Welds
CF, SCC
Design (water piston), residual welding stress, operation, water chemistry
Y
10^7
LP Turbine Rotors and Disks
SCC
Design stresses, temperaturen, high strength steel, steam chemistry
Y
10^7
CF
Steam chemistry, design, vibration
N
LP Turbine Blades
CF
SCC
Steam chemistry, design vibration, pitting, erosion,
High strength steel
N
10^6
HP/IP Turbine Rotors
LCF
Cycling, inclusions, fatigue design
Y
10^7
Turbine
Destructive Overspeed
Steam chemistry (boiler carry-over) - sticking valves
Y
10^7 - 10^8
Turbine
Rubbing
Steam chemistry, deposits, thrust bearing wear, thermal expansion
Y

10^6


[1]
CF - Corrosion Fatigue               
LCF - Low Cycle Fatigue                   
LCCF - Low Cycle Corrosion Fatigue          
SCC - Stress Corrosion Cracking              
FAC - Flow-Accelerated Corrosion         
[2]
Age influences the degree of damage for all issues except the last two
[3]
At least one destructive failure during the last 30 years
[4]
Lost production and repairs per one event
Audit Description
Based on the industry experience and plant information gathered in advance and during the plant visit, critical components and their potential damage mechanisms are identified, existing inspection, maintenance, and operation practices are evaluated, and the needs for improvements and more detailed life evaluation and extension determined.

The audit is structured as follows:

1.
Information gathering - prior to visit
2.
Cycle and equipment design review - prior to visit
3.
Initial meeting - ~ 2 hours
4.
Review of plant experience - ~ 6 hours
5.
Review of operation, maintenance, NDT, water chemistry and corrosion control -
~ 2 days
6.
Preliminary Conclusions and Recommendations - provided before leaving the site
7.
Closing meeting:  a joint review of the Preliminary Conclusions and Recommendations - ~ 2 hours
8.
Audit Report - ~ 6 weeks after plant visit